This work, carried out between October 26 and November 10, 2026, followed the deterioration of the old Berlin wall-type retaining structure, progressively weakened by successive weather events. The objective was to secure and permanently stabilize this section of the bank.
A new piling technique was employed. After dismantling the old structure and removing some of the sand, 526 chestnut piles, each 5 meters long, were driven over 3.5 meters deep. This system ensures the anchoring and stability of the terrain over a length of 115 meters.
The choice of chestnut, rich in tannins, was favored for its rot-proof properties, offering natural resistance to moisture, fungi, and insects without chemical treatment.
The intervention concluded with re-sanding and the installation of a geotextile sheet to level the ground, thus helping to preserve the pleasant environment around the lake.