Started on 12 October 2026, the works extend mainly along Meyniel Boulevard, between 14-Juillet Square and the Lestang junction. Two additional interventions are also planned on Deluns-Montaud Street and between Libération Street and Petite Rue Touratte. The operation involves renovating the internal structures of the existing sewer to guarantee its strength and durability, while preparing for future network separation works (wastewater and stormwater).
Rehabilitation is carried out directly from inside the structure. After cleaning by hydro-jetting, the walls are prepared to remove debris and roots, then high-pressure cleaned. A coating is sprayed onto the internal walls and central gutters are installed to ensure water flow. To limit disruption, the project progresses in sections of 100 to 150 metres.
The end of the project is provisionally scheduled for 9 April 2027, subject to weather conditions. Works will be suspended during the end-of-year holidays, from the evening of Friday 18 December 2026, with a resumption planned for Monday 4 January 2027. A second phase of rehabilitation is scheduled for the second half of 2027 on Gambetta Boulevard.
Led by Val de Garonne Agglomeration, this operation represents an investment of 780,000 € TTC, funded equally by the Agglomeration (Water and Sanitation competence) and the City of Marmande (stormwater management). The work is entrusted to the company SUBTERRA, with project management assistance from Infraneo.