Basque Coast: coastal risk management strategy moves towards 2028

Review of 2023-2026 actions and preparation for the next steps in coastline adaptation.

Generic image of the Atlantic coast with cliffs and the ocean, no text or logos visible.
AI

Generic image of the Atlantic coast with cliffs and the ocean, no text or logos visible.

The steering committee for the local coastal risk management strategy (SLGRL) of the Basque Coast met on November 19, 2026, to review progress and prepare the next steps of the action programme, which continues until 2028.

Key points

  • 2023-2028 action programme led by the CAPB
  • Over €10 million committed for the 2025-2026 phase
Chaired by Emmanuel Alzuri, delegated councilor for the coast and shoreline, the meeting brought together nearly 50 participants, including elected officials from the 8 coastal municipalities, state services, the Nouvelle-Aquitaine Region, the Pyrénées-Atlantiques Department, the GIP Littoral, as well as associative and scientific stakeholders.
The committee allowed for a review of the technical and financial progress of the programme. The 2023-2024 phase saw the completion of the majority of planned actions for an amount of €7.5 million, thanks to European, regional, local, and state co-financing. For the 2025-2026 period, completed or initiated actions represent an estimated amount of over €10 million, with similar projected co-financing. A comprehensive financial and technical report will be produced in 2027.
Several topics were discussed in depth, particularly the updating of local maps projecting coastline retreat at 30 and 100 years, with integration into planning documents planned after the summer of 2027. The monitoring of coastline evolution, in partnership with the Nouvelle-Aquitaine Coast Observatory (OCNA), was also examined, particularly the lessons from the winter of 2025.
The meeting concluded with a visit to two municipal projects illustrating adaptation on the ground. In Bidart, the Prairie des Embruns demonstrates a renaturation and redevelopment approach for a former rugby field. In Saint-Jean-de-Luz, the Senix beach is the subject of an adaptation project aiming to reconcile coastline retreat adaptation, renaturation, and improved beach access, following the Erromardie redevelopment completed in spring 2026.
Based on information from the official source: GIP Littoral Nouvelle-Aquitaine (24/11/2026)